Under construction
ONYX BIZMARK 52
MahaRERA P52100020510High risk
by M/s.Onyx Noble Realtors LLP
52/7B/2, KONDHWA BK, 411048
Post your property hereOwn or renting out a unit in ONYX BIZMARK 52? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in KONDHWA BK come to you.
Mar 2023
Possession
81.8%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Mar 2023) has passed with construction at 81.8%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Mar 2023 per the RERA filing.
Promoter
Builder profile
M/s.Onyx Noble Realtors LLP
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100020510
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2023
- Construction
- 81.8% complete
- Units sold
- 0 of 0
Similar projects in KONDHWA BK
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
ALCON ROYCE
KONDHWA BK100% builtPoss. June 2019
SHREE SHANTINAGAR CO OPERATIVE HOUSING SOCIETY LIMITED
KONDHWA BK100% builtPoss. November 2025
CHORDIYA RESIDENCY
KONDHWA BK90.9% builtPoss. August 2026
RAGHUNANDAN KASTURI/ KAMTHE PATIL BUSINESS CENTER
KONDHWA BK81.8% builtPoss. May 2024
INDRAPRASTHA
KONDHWA BK81.8% builtPoss. June 2022
SNEH PRATIK
KONDHWA BK81.8% builtPoss. December 2024
CHORDIYA GALAXY
KONDHWA BK79.1% builtPoss. December 2025
VRUNDAVAN RESIDENCY
KONDHWA BK69.1% builtPoss. September 20261 complaint
Keep exploring
Where this project sits, who built it, and how KONDHWA BK compares.
In KONDHWA BK
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.