Under construction
ORCHID PARK
MahaRERA P52000016238High risk
SURVEY NO.169, PLOT NO.53, MAMDAPUR, 410101
Post your property hereOwn or renting out a unit in ORCHID PARK? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in MAMDAPUR come to you.
Dec 2022
Possession
86.8%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~3 yrs. Originally promised Dec 2019, now proposed Dec 2022 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 86.8%.
Satellite view of this address
Where it is · SURVEY NO.169, PLOT NO.53, MAMDAPUR
Promoter
Builder profile
UNITED ONE REALTY LLP
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52000016238
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2022originally December 2019
- Construction
- 86.8% complete
- Units sold
- 0 of 0
Similar projects in MAMDAPUR
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
GREEN VALLEY
MAMDAPURPoss. October 2027
ARENA ONE
MAMDAPURPoss. December 2028
BRAMHA HEIGHT
MAMDAPUR100% builtPoss. December 2021
SAI RESIDENCY
MAMDAPUR100% builtPoss. February 2021
SAI PALACE
MAMDAPUR100% builtPoss. March 2022
KAILASH APARTMENT
MAMDAPUR100% builtPoss. March 2023
SHIREEN PLAZA
MAMDAPUR90.9% builtPoss. March 2019
AFSHA APARTMENT
MAMDAPUR90.9% builtPoss. March 2022
Keep exploring
Where this project sits, who built it, and how MAMDAPUR compares.
In MAMDAPUR
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.