Dec 2022
Possession
27.3%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~1 yr. Originally promised Dec 2021, now proposed Dec 2022 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 27.3%.
- Promised amenities not started. Swimming Pool, Gymnasium, Landscaped Garden are at 0% build with possession due Dec 2022 per the RERA filing.
Promoter
Builder profile
SAMARJEET TULAJIRAO INDULKAR
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P51600018076
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2022originally December 2021
- Construction
- 27.3% complete
- Units sold
- 0 of 0
Similar projects in IGATPURI
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
S.No. 397-1
IGATPURIPoss. March 2018
ANANDVANN
IGATPURI100% builtPoss. December 20191 complaint
BHUJARI TOWER
IGATPURI100% builtPoss. May 2019
MADHUBAN PARK
IGATPURI90.9% builtPoss. June 2024
EMPIRE
IGATPURI72.4% builtPoss. December 20236 complaints
SITA ARCADE
IGATPURI55.5% builtPoss. December 2024
SATKAR RESIDENCY
IGATPURI39.5% builtPoss. December 2026
AEROSOL
IGATPURI0% builtPoss. December 2026