Under construction

OXY FLORA PHASE 2

MahaRERA P52100015940High risk

by OXY FLORA PHASE 2

GAT NO 271,272,275,277,278, LONIKAND, 412216

Official record
Dec 2022
Possession
37.5%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~1 yr. Originally promised Dec 2021, now proposed Dec 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 37.5%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2022 per the RERA filing.
Satellite view of this address

Where it is · GAT NO 271,272,275,277,278, LONIKAND

Promoter

Builder profile

Builder
OXY FLORA PHASE 2

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100015940
Status
New
Stage
Certificate Signed
Possession
December 2022originally December 2021
Construction
37.5% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how LONIKAND compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.