PADMAVATI NAGARI BLDG NO 1 A and B wing

MahaRERA P51600003238High risk

by S D BHALERAO CONSTRUCTIONS PVT LTD

GUT NO 162 PLOT NO 15 TO 18 AND 35 TO 38, Venkatesh Nagar, 422403

Official record
Oct 2020
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2018, now proposed Oct 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 90.9%.
Satellite view of this address

Where it is · GUT NO 162 PLOT NO 15 TO 18 AND 35 TO 38, Venkatesh Nagar

Area guide

What it's like to buy in Venkatesh Nagar

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
S D BHALERAO CONSTRUCTIONS PVT LTD

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600003238
Status
Ongoing
Stage
Certificate Signed
Possession
October 2020originally December 2018
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Venkatesh Nagar

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Venkatesh Nagar compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.