High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • Possession delayed ~1 yr. Originally promised Dec 2024, now proposed Jun 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 76.1%.
Satellite view of this address

Where it is · 65/1A/1D, Ghorpadi

Promoter

Builder profile

Builder
Cedrus Assets

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100010652
Status
Ongoing
Stage
Certificate Signed
Possession
June 2026originally December 2024
Construction
76.1% complete
Units sold
0 of 0

Similar projects in Ghorpadi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Ghorpadi compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.