High risk
  • Possession date passed. The proposed possession date (Mar 2024) has passed with construction at 48.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2024 per the RERA filing.
Satellite view of this address

Where it is · 12A 7296/31 AND 32 7303, NEAR BARAMATI BANK

Promoter

Builder profile

Builder
BUILDCON DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100045480
Status
New
Stage
Certificate Signed
Possession
March 2024
Construction
48.7% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how NEAR BARAMATI BANK compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.