Paras Residency
141/A, Goregaon W, 400104
- Litigation pending (3). MahaRERA's litigation disclosure lists 3 pending cases against this project.
- Possession delayed ~1 yr. Originally promised Sept 2025, now proposed Nov 2026 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2026 per the RERA filing.
Where it is · 141/A, Goregaon W
Area guide
What it's like to buy in Goregaon W
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Film City flank with large integrated townships on both flanks.
- Growth drivers:
- Oberoi/NESCO belt, Metro 7, Western Express Highway offices.
- Who buys here:
- Upgraders wanting township amenities without Powai prices.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P51800046023
- Status
- New
- Stage
- Certificate Signed
- Possession
- November 2026originally September 2025
- Construction
- 90.9% complete
- Units sold
- 6 of 48
Keep exploring
Where this project sits, who built it, and how Goregaon W compares.
In Goregaon W
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.