Nov 2023
Possession
65.5%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Nov 2023) has passed with construction at 65.5%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Nov 2023 per the RERA filing.
Satellite view of this address
Where it is · 31 3A, 32 1A, 31 4, 31 3B2, BALEWADI
Promoter
Builder profile
SHARADA ALLIANCE SHELTERS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100023380
- Status
- New
- Stage
- Certificate Signed
- Possession
- November 2023
- Construction
- 65.5% complete
- Units sold
- 0 of 0
Similar projects in BALEWADI
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Comfort Zone Bliss
BALEWADIPoss. October 2027
PRIVILEGE STUDIOS
BALEWADIPoss. April 2031
The Midas Residences Phase 5
BALEWADIPoss. June 2030
The Midas Residences Phase 6
BALEWADIPoss. June 2031
SIYA APARTMENT II
BALEWADI100% builtPoss. December 2019
MAJESTIQUE SIGNATURE TOWERS PHASE 1
BALEWADI100% builtPoss. September 20242 complaints
MAJESTIQUE SIGNATURE TOWERS C2
BALEWADI100% builtPoss. June 2025
MANTRA MONARCH PHASE 2
BALEWADI100% builtPoss. June 2026
Keep exploring
Where this project sits, who built it, and how BALEWADI compares.
In BALEWADI
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.