High risk
  • Behind schedule. Possession is due May 2027 but construction is only at 8.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due May 2027 per the RERA filing.
Satellite view of this address

Where it is · SR NO 27/A/1 27/2 25/B/1, DEOLALI CAMP

Promoter

Builder profile

Builder
UTTAM AMBADAS RAI

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600021087
Status
New
Stage
Certificate Signed
Possession
May 2027
Construction
8.6% complete
Units sold
0 of 0

Similar projects in DEOLALI CAMP

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.