Under construction

Park Marina Building B and C

MahaRERA P52100004085High risk

by SUJAY ASSOCIATES

S No 137 1 137 2 138 1 1 138 3 139 1, Baner, 411045

Official record
Mar 2019
Possession
40.9%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 40.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2019 per the RERA filing.
Satellite view of this address

Where it is · S No 137 1 137 2 138 1 1 138 3 139 1, Baner

Area guide

What it's like to buy in Baner

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
SUJAY ASSOCIATES

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100004085
Status
Ongoing
Stage
Certificate Signed
Possession
March 2019originally March 2018
Construction
40.9% complete
Units sold
0 of 0

Similar projects in Baner

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Baner compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.