High risk
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~2 yrs. Originally promised Jan 2023, now proposed Dec 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 99.8%.

Promoter

Builder profile

Builder
Gaiagen Technologies Private Limited

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
DA DESIGNS

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51800031874
Status
New
Stage
Certificate Signed
Possession
December 2024originally January 2023
Construction
99.8% complete
Units sold
92 of 158

Similar projects in Dahisar West

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Dahisar West compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.