PARK59
259/4 1945 1952 2706 2712 2713 2721 2732 2733 2705 1947, Mulshi, 411057
- Possession delayed ~2 yrs. Originally promised Sept 2026, now proposed Apr 2028 per the RERA filing.
Where it is · 259/4 1945 1952 2706 2712 2713 2721 2732 2733 2705 1947, Mulshi
Area guide
What it's like to buy in Mulshi
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100024649
- Status
- New
- Stage
- Certificate Signed
- Possession
- April 2028originally September 2026
- Construction
- 87.2% complete
- Units sold
- 139 of 230
Similar projects in Mulshi
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Mulshi compares.
In Mulshi
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.