PARKSYDE NEST PHASE-3A
256/2 to 6/2 256/2 to 6/3 256/2 to 6/4 256/2 to 6/5 256/2 to 6/8P, PANCHAVATI ANNEX, 422003
- Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 92.3%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2025 per the RERA filing.
Where it is · 256/2 to 6/2 256/2 to 6/3 256/2 to 6/4 256/2 to 6/5 256/2 to 6/8P, PANCHAVATI ANNEX
Area guide
What it's like to buy in PANCHAVATI ANNEX
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51600033065
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2025
- Construction
- 92.3% complete
- Units sold
- 0 of 0
Similar projects in PANCHAVATI ANNEX
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how PANCHAVATI ANNEX compares.
In PANCHAVATI ANNEX
The developer
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.