High risk
  • Mortgaged to a lender (₹25 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹25 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • 6 RERA complaints. 6 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · 165/1Apt, 166/6Apt, 166/8Apt, D-Mart, Kavesar

Area guide

What it's like to buy in D-Mart

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Aniline Construction Company Private Limited

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Saakaar

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51700007024
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally March 2026
Construction
65.1% complete
Units sold
420 of 420

Keep exploring

Where this project sits, who built it, and how D-Mart, Kavesar compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.