Patel Mount
S.No.42A, Hissa No. 2(pt),3(pt),(4pt),7(pt),8(pt),9(pt),24(pt), S.No.41A, Hissa No.1(pt),2(pt), Chikanghar, Kalyan West, 421301
- Possession delayed ~3 yrs. Originally promised Jun 2024, now proposed Dec 2026 per the RERA filing.
- Behind schedule. Possession is due Dec 2026 but construction is only at 49%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.
Where it is · S.No.42A, Hissa No. 2(pt),3(pt),(4pt),7(pt),8(pt),9(pt),24(pt), S.No.41A, Hissa No.1(pt),2(pt), Chikanghar, Kalyan West
Area guide
What it's like to buy in Chikanghar
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Central-line volume market — affordable towers around busy junctions.
- Growth drivers:
- Metro 5, ring-road plans, the region's most accessible pricing.
- Who buys here:
- Budget-first buyers who commute the central line.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P51700048299
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally June 2024
- Construction
- 49% complete
- Units sold
- 26 of 81
Similar projects in Chikanghar
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Chikanghar, Kalyan West compares.
In Chikanghar, Kalyan West
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.