- Behind schedule. Possession is due Dec 2026 but construction is only at 32.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Where it is · SURVEY NO.50 HISSA NO.6 CTS NO.7749 TO 7754 (PART) SURVEY NO.50 HISSA NO.13 CTS NO.7746 TO 7748 and 7754 (PART), AMBERNATH EAST
Area guide
What it's like to buy in AMBERNATH EAST
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
The value frontier beyond Kalyan — low-rise affordability, improving rail links.
- Growth drivers:
- Extended suburban rail, industrial-belt employment, lowest entry prices in MMR.
- Who buys here:
- First-home buyers stretching every rupee.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700055979
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 32.5% complete
- Units sold
- 0 of 0
Similar projects in AMBERNATH EAST
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how AMBERNATH EAST compares.
In AMBERNATH EAST
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.