High risk
  • Mortgaged to a lender (₹20 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹20 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Possession delayed ~9 yrs. Originally promised Mar 2019, now proposed Mar 2028 per the RERA filing.
Satellite view of this address

Where it is · S NO 73, Haveli

Promoter

Builder profile

Builder
KRISH DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100003546
Status
Ongoing
Stage
Certificate Signed
Possession
March 2028originally March 2019
Construction
56.8% complete
Units sold
28 of 173

Similar projects in Haveli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Haveli compares.

Data sourced from the official MahaRERA portal; complaints last synced 8 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.