High risk
  • Possession delayed ~9 yrs. Originally promised Dec 2019, now proposed Dec 2028 per the RERA filing.
Satellite view of this address

Where it is · 424, Lonavala

Area guide

What it's like to buy in Lonavala

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
AMIR VEERJI BHANWADIA

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100002473
Status
New
Stage
Certificate Signed
Possession
December 2028originally December 2019
Construction
47.3% complete
Units sold
3 of 10

Similar projects in Lonavala

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Lonavala compares.

Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.