High risk
- 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession date passed. The proposed possession date (May 2026) has passed with construction at 4.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due May 2026 per the RERA filing.
Satellite view of this address
Where it is · sector 4, 8, Sudhagad
Promoter
Builder profile
Phase 1
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52000017655
- Status
- New
- Stage
- Certificate Signed
- Possession
- May 2026
- Construction
- 4.5% complete
- Units sold
- 0 of 0
Similar projects in Sudhagad
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Kshitijs Woods
SudhagadPoss. December 20253 complaints
City Of Music Phase II
SudhagadPoss. June 20265 complaints
HILLS N MILLS
SudhagadPoss. December 2020
LAKE CITY PHASE-4
SudhagadPoss. June 2022
TECTONA HILLS
SudhagadPoss. December 2028
JOY VILLA PHASE-2
SudhagadPoss. November 2023
CITY OF MUSIC PHASE IV
SudhagadPoss. December 2026
Nirvana Bougainvilla
SudhagadPoss. December 20271 complaint
Keep exploring
Where this project sits, who built it, and how Sudhagad compares.
In Sudhagad
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.