High risk
  • Possession delayed ~6 yrs. Originally promised Dec 2022, now proposed Dec 2028 per the RERA filing.
  • High complaint rate. 3 complaints against only 9 sold units — a high rate for a project this size.

Area guide

What it's like to buy in NALLASOPARA (WEST)

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
SHREE BALAJI DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P99000022803
Status
New
Stage
Certificate Signed
Possession
December 2028originally December 2022
Construction
47.7% complete
Units sold
9 of 31

Similar projects in NALLASOPARA (WEST)

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how NALLASOPARA (WEST) compares.

Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.