High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Apr 2027 per the RERA filing.
  • 10 RERA complaints. 10 complaint records are disclosed against this project on MahaRERA.
  • Behind schedule. Possession is due Apr 2027 but construction is only at 46.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · 37 2 1 40 2 1 40 2 2, Haveli

Promoter

Builder profile

Builder
Ranjeet Property Developers India Pvt. Ltd.

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100007013
Status
Ongoing
Stage
Certificate Signed
Possession
April 2027originally December 2022
Construction
46.4% complete
Units sold
0 of 0

Similar projects in Haveli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Haveli compares.

Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.