Under construction

PLATINUM TOWER - 1

MahaRERA P51800000487High risk

by AKSHAY GRUHPRAVESH LLP

195 PT , SURVEY NO 106/1A,1/6A, Andheri, 400058

Official record
Mar 2022
Possession
90.9%
Built
1
Complaints
0
Units
High risk
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~2 yrs. Originally promised Mar 2020, now proposed Mar 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 90.9%.
Satellite view of this address

Where it is · 195 PT , SURVEY NO 106/1A,1/6A, Andheri

Area guide

What it's like to buy in Andheri

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Andheri East / MarolMid-income

Office corridors (SEEPZ, MIDC) with value housing pockets between them.

Growth drivers:
Airport proximity, Metro 1/7, IT-park employment.
Who buys here:
Working couples prioritising commute over frills.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
AKSHAY GRUHPRAVESH LLP

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800000487
Status
Ongoing
Stage
Certificate Signed
Possession
March 2022originally March 2020
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Andheri

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Andheri compares.

Data sourced from the official MahaRERA portal; complaints last synced 20 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.