🏗️
Under construction

PLATINUM TOWER - 7

MahaRERA P51800000654High risk

by TIRUPATI GRUHPRAVESH LLP

195 PT , SURVEY NO 106 /1A,1/6A, Andheri, 400058

Official record
Dec 2020
Possession
90.9%
Built
2
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2019, now proposed Dec 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 90.9%.
Satellite view of this address

Where it is · 195 PT , SURVEY NO 106 /1A,1/6A, Andheri

Area guide

What it's like to buy in Andheri

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Andheri WestUpper-mid

Entertainment-industry heartland — dense, lively, well connected.

Growth drivers:
Metro lines 1/2A, Lokhandwala–Versova redevelopment wave.
Who buys here:
Media professionals, first upgraders, rental investors.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
TIRUPATI GRUHPRAVESH LLP

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800000654
Status
Ongoing
Stage
Certificate Signed
Possession
December 2020originally June 2019
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Andheri

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Andheri compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.