  • Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 72.7%.
Satellite view of this address

Where it is · 19/28 19/29 19/30 20/05 21/16 20/06, Thane

Promoter

Builder profile

Builder
Haware's Housing Development Finance Corporation Ltd.

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700000549
Status
Ongoing
Stage
Certificate Signed
Possession
June 2023originally September 2022
Construction
72.7% complete
Units sold
0 of 0

Similar projects in Thane

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Thane compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.