All RERA projects
🏗️
Under construction

PMAY SCHEME AT SURVEY NO 106A/12B/3B PART HADAPSAR, TAL HAVELI, DIST PUNE

MahaRERA P52100026784High risk

by PMAY CELL,PUNE MUNICIPAL CORPORATION

SURVEY NO 106A/12B/3B PART, HADAPSAR, 411028

Official record
Jun 2024
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2024 per the RERA filing.

Area guide

What it's like to buy in HADAPSAR

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
PMAY CELL,PUNE MUNICIPAL CORPORATION

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100026784
Status
New
Stage
Certificate Signed
Possession
June 2024
Construction
90.9% complete
Units sold
0 of 0

Similar projects in HADAPSAR

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how HADAPSAR compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.