All RERA projects
🏗️
Under construction

PMAY SCHEME AT SURVEY NO 89 PART AND 92 PART PLOT E, HADAPSAR, TAL HAVELI, DIST PUNE

MahaRERA P52100029030Caution

by PMAY CELL,PUNE MUNICIPAL CORPORATION

SURVEY NO 89 PART AND 92 PART, PLOT E, Haveli, 411028

Official record
Apr 2027
Possession
40.9%
Built
0
Complaints
0
Units
Caution
  • Behind schedule. Possession is due Apr 2027 but construction is only at 40.9%.

Area guide

What it's like to buy in Haveli

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
PMAY CELL,PUNE MUNICIPAL CORPORATION

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100029030
Status
New
Stage
Certificate Signed
Possession
April 2027originally December 2026
Construction
40.9% complete
Units sold
0 of 0

Similar projects in Haveli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Haveli compares.

Data sourced from the official MahaRERA portal; complaints last synced 19 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.