Dec 2026
Possession
0%
Built
1
Complaints
675
Units
High risk
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~2 yrs. Originally promised Mar 2025, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 0%.
  • Promised amenities not started. Swimming Pool, Gymnasium, Clubhouse are at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · S NO 9 HISSA NO 3, 1/B & 2, S NO 10,S NO 11 HISSA NO. 1&2, MHARAL

Area guide

What it's like to buy in MHARAL

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Poddar Housing and Development Limited

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700023296
Status
New
Stage
Certificate Signed
Possession
December 2026originally March 2025
Construction
0% complete
Units sold
53 of 675

Similar projects in MHARAL

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how MHARAL compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.