High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2019, now proposed Jun 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2025) has passed with construction at 56.9%.
Satellite view of this address

Where it is · Gat no 1205/1C, Talegaon

Promoter

Builder profile

Builder
Primary Housing Corporation LLP

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100000382
Status
New
Stage
Certificate Signed
Possession
June 2025originally December 2019
Construction
56.9% complete
Units sold
0 of 0

Similar projects in Talegaon

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Talegaon compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.