  • Possession delayed ~2 yrs. Originally promised Mar 2025, now proposed Jul 2027 per the RERA filing.
  • Behind schedule. Possession is due Jul 2027 but construction is only at 45%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2027 per the RERA filing.
Satellite view of this address

Where it is · 637/8, 131/B, Andheri

Promoter

Builder profile

Builder
JPV PEARL LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51800032248
Status
New
Stage
Certificate Signed
Possession
July 2027originally March 2025
Construction
45% complete
Units sold
5 of 20

Similar projects in Andheri

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Andheri compares.

Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.