High risk
  • Litigation pending (9). MahaRERA's litigation disclosure lists 9 pending cases against this project.
  • Possession delayed ~2 yrs. Originally promised Oct 2024, now proposed Oct 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2026 per the RERA filing.
Satellite view of this address

Where it is · 81A 81A 3 TO 51 81C PT, Andheri

Area guide

What it's like to buy in Andheri

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Andheri WestUpper-mid

Entertainment-industry heartland — dense, lively, well connected.

Growth drivers:
Metro lines 1/2A, Lokhandwala–Versova redevelopment wave.
Who buys here:
Media professionals, first upgraders, rental investors.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
PREM BUILDERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800013919
Status
New
Stage
Certificate Signed
Possession
October 2026originally October 2024
Construction
72.3% complete
Units sold
186 of 321

Similar projects in Andheri

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Andheri compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.