High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · CTS No 61C Part, 61C/122-125, Chembur

Area guide

What it's like to buy in Chembur

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Kurla / ChemburMid-income

Central crossroads reborn via freeway and Metro links.

Growth drivers:
Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
Who buys here:
BKC-bound professionals and long-time Chembur families.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Panache Developers Pvt Ltd.

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
RAIZADA DESIGNS

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51800008982
Status
New
Stage
Certificate Signed
Possession
April 2027originally December 2023
Construction
88.7% complete
Units sold
117 of 579

Similar projects in Chembur

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Chembur compares.

Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.