  • Possession delayed ~2 yrs. Originally promised Dec 2025, now proposed Jun 2028 per the RERA filing.
Satellite view of this address

Where it is · GAT NO 1346/1, GAT NO 1346/1, WAGHOLI

Promoter

Builder profile

Builder
SHAKUNTALA CHANDRASHEKHAR GONNAGAR

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100054172
Status
New
Stage
Certificate Signed
Possession
June 2028originally December 2025
Construction
41.9% complete
Units sold
11 of 15