Prozone Palms
by Hagwood Commercial Developers Private Limited
Plot No 1A Kh No 25, 29, 30, CTS No 78, 79, 88 Sheet No 745, 744, 741, 742, 739, 738, 633, 634, CHINCHBHUVAN, 440025
- Litigation pending (3). MahaRERA's litigation disclosure lists 3 pending cases against this project.
- 18 appeals at MahaREAT. 18 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession delayed ~9 yrs. Originally promised Dec 2018, now proposed Jul 2027 per the RERA filing.
- 96 RERA complaints. 96 complaint records are disclosed against this project on MahaRERA.
Where it is · Plot No 1A Kh No 25, 29, 30, CTS No 78, 79, 88 Sheet No 745, 744, 741, 742, 739, 738, 633, 634, CHINCHBHUVAN
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
No other projects are linked to this architect yet.
Official RERA facts
- Registration
- P50500004915
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- July 2027originally December 2018
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in CHINCHBHUVAN
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how CHINCHBHUVAN compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 20 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.