Caution
  • Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 81.8%.
Satellite view of this address

Where it is · 119 and 119 1, Chembur Mumbai

Area guide

What it's like to buy in Chembur Mumbai

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Kurla / ChemburMid-income

Central crossroads reborn via freeway and Metro links.

Growth drivers:
Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
Who buys here:
BKC-bound professionals and long-time Chembur families.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
SUDHIR VASU SHETTY

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51800006305
Status
Ongoing
Stage
Certificate Signed
Possession
March 2019originally March 2018
Construction
81.8% complete
Units sold
0 of 0