Under construction

QUEENS VILLA

MahaRERA P99000005836High risk

by SHASHI KULDEEP OSTWAL

SURVEY NO 158 HISSA NO.1 PLOT NO. 80, 81, 83, 84, Palghar, 401501

Official record
Jul 2026
Possession
40.3%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jul 2026) has passed with construction at 40.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2026 per the RERA filing.
Satellite view of this address

Where it is · SURVEY NO 158 HISSA NO.1 PLOT NO. 80, 81, 83, 84, Palghar

Promoter

Builder profile

Builder
SHASHI KULDEEP OSTWAL

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P99000005836
Status
Ongoing
Stage
Certificate Signed
Possession
July 2026
Construction
40.3% complete
Units sold
0 of 0

Similar projects in Palghar

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Palghar compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.