High risk
  • Possession date passed. The proposed possession date (Mar 2025) has passed with construction at 70.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2025 per the RERA filing.
Satellite view of this address

Where it is · SR NO.53 Hissa No 5, SR NO.53, HISSA NO 5, BAVDHAN KHURD

Promoter

Builder profile

Builder
LOHIA JAIN REALTY LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100034344
Status
New
Stage
Certificate Signed
Possession
March 2025
Construction
70.9% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how SR NO.53, HISSA NO 5, BAVDHAN KHURD compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.