High risk
  • Possession delayed ~1 yr. Originally promised Oct 2020, now proposed Apr 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Apr 2022) has passed with construction at 60%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2022 per the RERA filing.
Satellite view of this address

Where it is · Gut No. 813, Vadgaon Anand.(Aalephata)

Promoter

Builder profile

Builder
Radha Housing

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100017411
Status
Ongoing
Stage
Certificate Signed
Possession
April 2022originally October 2020
Construction
60% complete
Units sold
0 of 0