Under construction

Radhe Govind Commercial Complex

MahaRERA P51700045967High risk

by Shree Radha Construction

Gut No.59 (P),(C.T.S.No.9004), Morivali Ambarnath, 421501

Official record
Dec 2026
Possession
34.1%
Built
0
Complaints
40
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 34.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · Gut No.59 (P),(C.T.S.No.9004), Morivali Ambarnath

Area guide

What it's like to buy in Morivali Ambarnath

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Ambernath / BadlapurValue

The value frontier beyond Kalyan — low-rise affordability, improving rail links.

Growth drivers:
Extended suburban rail, industrial-belt employment, lowest entry prices in MMR.
Who buys here:
First-home buyers stretching every rupee.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Shree Radha Construction

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Satish Kanade

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51700045967
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2023
Construction
34.1% complete
Units sold
4 of 40