Under construction

Rahul Downtown - Phase I

MahaRERA P52100045552High risk

by Paras Multispace LLP

11/10/1+11/11/1 to 11/11/10+11/12+11/13, Punawale, 411033

Official record
Jul 2025
Possession
83%
Built
2
Complaints
392
Units
High risk
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession date passed. The proposed possession date (Jul 2025) has passed with construction at 83%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2025 per the RERA filing.

Area guide

What it's like to buy in Punawale

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Paras Multispace LLP

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Pandit Joshi & Associates

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100045552
Status
New
Stage
Certificate Signed
Possession
July 2025originally April 2025
Construction
83% complete
Units sold
349 of 392

Similar projects in Punawale

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Punawale compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.