High risk
  • Litigation pending (3). MahaRERA's litigation disclosure lists 3 pending cases against this project.
  • Possession delayed ~3 yrs. Originally promised Sept 2020, now proposed Jun 2023 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 81.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2023 per the RERA filing.
Satellite view of this address

Where it is · 504, Parvati

Promoter

Builder profile

Builder
Siddh Construction and Developers

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100019158
Status
Ongoing
Stage
Certificate Signed
Possession
June 2023originally September 2020
Construction
81.8% complete
Units sold
0 of 0

Similar projects in Parvati

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Parvati compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.