High risk
  • Possession delayed ~2 yrs. Originally promised Mar 2019, now proposed Sept 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2020) has passed with construction at 72.7%.
Satellite view of this address

Where it is · CTS NUMBER 6345 TO 6347 , Haveli

Promoter

Builder profile

Builder
RAISONI BUILDARS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100004785
Status
Ongoing
Stage
Certificate Signed
Possession
September 2020originally March 2019
Construction
72.7% complete
Units sold
0 of 0

Similar projects in Haveli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Haveli compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.