High risk
  • Possession delayed ~7 yrs. Originally promised Oct 2020, now proposed Oct 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2027 per the RERA filing.
Satellite view of this address

Where it is · GUT NO 164 AND 166, PALGHAR

Promoter

Builder profile

Builder
RAJSHREE REALTY

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P99000014145
Status
Ongoing
Stage
Certificate Signed
Possession
October 2027originally October 2020
Construction
65.9% complete
Units sold
0 of 0

Similar projects in PALGHAR

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how PALGHAR compares.

Data sourced from the official MahaRERA portal; complaints last synced 11 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.