Under construction

RAUNAK BLISS A4

MahaRERA P51700046674High risk

by UNNATHI ASSOCIATES

21/1,3,4,5,6,7,8A,8B, 72/8,71/1,66/1,2,4,6,7,8,9,10,11,12,13,14,15,16,17,65/1,65/2, Vadawali & Owale, 400615

Official record
Dec 2029
Possession
72.3%
Built
4
Complaints
273
Units
High risk
  • Litigation pending (5). MahaRERA's litigation disclosure lists 5 pending cases against this project.
Satellite view of this address

Where it is · 21/1,3,4,5,6,7,8A,8B, 72/8,71/1,66/1,2,4,6,7,8,9,10,11,12,13,14,15,16,17,65/1,65/2, Vadawali & Owale

Area guide

What it's like to buy in Vadawali & Owale

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
UNNATHI ASSOCIATES

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
SUBHASH GUPTE

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51700046674
Status
New
Stage
Certificate Signed
Possession
December 2029
Construction
72.3% complete
Units sold
254 of 273

Keep exploring

Where this project sits, who built it, and how Vadawali & Owale compares.

Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.