Under construction
RAVI OMKAR ESTATE
MahaRERA P99000078719Caution
SURVEY NO.37, PLOT NO. 16/B AND 17/2, VASAI EAST, 401208
Post your property hereOwn or renting out a unit in RAVI OMKAR ESTATE? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in VASAI EAST come to you.
Dec 2026
Possession
77.3%
Built
0
Complaints
0
Units
Caution
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Area guide
What it's like to buy in VASAI EAST
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
OMKAR ENTERPRISES
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P99000078719
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 77.3% complete
- Units sold
- 0 of 0
Similar projects in VASAI EAST
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
SKY HEIGHTS
VASAI EAST90.9% builtPoss. March 2025
GREG MARSH RESIDENCY
VASAI EAST90.9% builtPoss. December 2021
GLADIOLUS TOWER
VASAI EAST90.5% builtPoss. December 2025
SAMAIRA RESIDENCY
VASAI EAST90.3% builtPoss. December 2026
ELITE TOWER
VASAI EAST87.6% builtPoss. March 2027
SIMANDHAR INDUSRIAL ESTATE
VASAI EAST81.8% builtPoss. October 2024
MAULI RESIDENCY
VASAI EAST66.4% builtPoss. December 2027
KARMA HEIGHTS
VASAI EAST64.9% builtPoss. June 2024
Keep exploring
Where this project sits, who built it, and how VASAI EAST compares.
In VASAI EAST
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.