RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD
OLD CTS NO 443 A PART AND NEW CTS NO 443 A1B1 AND 443 A1B2, Gavanpada, 400081
- Possession delayed ~9 yrs. Originally promised Jul 2019, now proposed Apr 2028 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2028 per the RERA filing.
Where it is · OLD CTS NO 443 A PART AND NEW CTS NO 443 A1B1 AND 443 A1B2, Gavanpada
Area guide
What it's like to buy in Gavanpada
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P51800002621
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- April 2028originally July 2019
- Construction
- 44.5% complete
- Units sold
- 8 of 36
Keep exploring
Where this project sits, who built it, and how Gavanpada compares.
In Gavanpada
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 25 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.