High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 90.9%.
Satellite view of this address

Where it is · 5/2p,5/2p,5/1p/1, Bhadwad Temghar Pada

Promoter

Builder profile

Builder
SQUAREFEET INFRASTRUCTURE LLP

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700008143
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021
Construction
90.9% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how Bhadwad Temghar Pada compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.