High risk
  • Possession delayed ~8 yrs. Originally promised Apr 2020, now proposed Apr 2028 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2028 per the RERA filing.
Satellite view of this address

Where it is · 1602, 1605 to 1608, Chinchavsli (Shekin)

Promoter

Builder profile

Builder
Concept Realtors

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52000012945
Status
Ongoing
Stage
Certificate Signed
Possession
April 2028originally April 2020
Construction
47.3% complete
Units sold
0 of 0