High risk
  • Litigation pending (5). MahaRERA's litigation disclosure lists 5 pending cases against this project.
  • 9 RERA complaints. 9 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Oct 2026 per the RERA filing.
Satellite view of this address

Where it is · S No 16/2A,17/1, 17/3, 17/4 and 17/5, Haveli

Area guide

What it's like to buy in Haveli

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Duville Estates Private Limited

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100029023
Status
New
Stage
Certificate Signed
Possession
October 2026originally June 2026
Construction
50.5% complete
Units sold
466 of 470

Similar projects in Haveli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Haveli compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.