All RERA projects
🏗️
Under construction

RKH Blessings B andd C building

MahaRERA P52100006496High risk

by RKH DEVELOPERS

72/1, Moshi, 412114

Official record
Aug 2023
Possession
21.1%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Aug 2023) has passed with construction at 21.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2023 per the RERA filing.
Satellite view of this address

Where it is · 72/1, Moshi

Promoter

Builder profile

Builder
RKH DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100006496
Status
Ongoing
Stage
Certificate Signed
Possession
August 2023
Construction
21.1% complete
Units sold
0 of 0

Similar projects in Moshi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Moshi compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.